This project involved the demolition of existing office spaces and a completely new fitout as designed for the BOPDHB.

The ground floor area covered 300m2 and the first floor area covered 600m2 of new office layout. Hawes Building Solutions Ltd was selected to complete this project due to its ability to deliver a project on time and on budget.

As the building had to remain occupied during the construction works, Hawes Building Solutions' expertise in staging and programming the works was also a key factor in its appointment. The floor areas were divided into stages enabling a new area to be handed over to the client so that work could commence on the next area.

The fitout used a combination of timber framing and linings, full height glazing and also prefabricated screens to form specifically designed work stations.

Special attention was paid to keeping all facilities operational, including phone, data and fire protection facilities.

The job was handed over exactly on time and to the clients satisfaction. Excellent feedback was received from all involved.